NORWAY —PSW Power & Automation AS, a subsidiary of Scana ASA, has received a substantial call-off order under its existing framework agreement with Tydal Data Center AS in Norway. The order covers the supply of frequency converter and transformer skids with a combined capacity of 240 MW for the data centre's battery energy storage system (BESS).
The equipment will perform power conversion and control functions across the complete battery storage installation. Frequency converters and transformers are essential components of large-scale energy storage infrastructure, enabling electrical power to be managed and integrated with the facility's power systems. The contracted scope therefore covers critical electrical infrastructure required for the data centre's battery storage operations.
The order is classified as substantial under Scana's contract reporting categories, corresponding to a value between NOK 75 million and NOK 150 million. The company has not disclosed the exact contract value. Work is expected to start immediately, while equipment deliveries are planned to commence in the first quarter of 2027.
The development highlights the growing demand for specialized electrical equipment as data centre operators expand power infrastructure and integrate battery energy storage systems. Large data centres require substantial and reliable electricity supplies, while storage installations can support energy management, power balancing and operational resilience. The 240 MW equipment scope represents a significant electrical infrastructure requirement within the Tydal facility.
For Norway's data centre and energy infrastructure sectors, the order creates demand for power conversion equipment, transformer systems and associated engineering capabilities. It also demonstrates the role of industrial automation and electrical engineering suppliers in supporting the expansion of energy-intensive digital infrastructure. Equipment manufacturers and suppliers involved in transformers, converters and battery storage integration may benefit from similar investment requirements across the sector.
For Scana, the call-off order converts an existing framework agreement into a defined delivery assignment and adds to its contracted activity in power and automation systems. The scheduled deliveries extending into 2027 provide visibility over upcoming manufacturing and supply activities. Scana ASA is a Norwegian industrial group operating through businesses focused on technology, engineering and equipment for energy and maritime-related markets. Its subsidiary PSW Power & Automation specializes in electrical power systems and automation solutions for industrial applications.